SASKPOWER OPEN HOUSE

Join us to learn more about the new power lines and a new switching station we’re building to improve power reliability in the Meadow Lake, Glaslyn and Spruce Lake areas.

Sask Power Open House

WHAT WE’RE BUILDING

  • a new switching station southwest of the existing one located south of Meadow Lake.
  • a new 230 kilovolt (kV) power line that will be about 16 kilometres long to connect an existing 230 kV power line in the area to the new switching station.
  • a new 138 kV power line that will be about 4 kilometres long to connect an existing 138 kV power line in the area to the new switching station.
  • a new 138 kV power line that will be about 100 kilometres long to extend an existing line from the Spruce Lake Switching Station to the new switching station.

Consultation is on-going with local officials, landowners, rightsholders and the general public to gather the information needed to select a preferred route for the new transmission lines. We invite anyone interested in this project to attend to learn about our plans for this project, ask questions and provide feedback.

For additional information or questions about the project, please contact us at 1-833-223-3370 or PublicEngagement@saskpower.com.